Following a £1.5 million grant from the Government Regional Growth Fund, BOC constructed a Dissolved Acetylene Plant next to it’s existing Special Gases plant in North Lincolnshire. This facility provides BOC with a strategic production facility to serve up to 160,000 customers in the UK.
Whilst Spencer undertook the building construction works, All Pump Solutions supplied a bespoke package pumping station combining 3 no. Flygt variable speed driven submersible pumps capable of pumping 300L/sec along with 3 no. 4m diameter GRP valve chambers including all the internal discharge pipework, non-return and actuated isolation valves, flow meter and pressure gauge.
All chambers were factory fitted, saving many hours on site and preventing health and safety issues. The modern facilities and technology at APS enabled the supply of complex valve chambers with up to 500mm diameter pipework in epoxy coated, ductile iron or stainless steel.